NOOSA PARADE RISING SEWER MAIN UPGRADE

SUNSHINE COAST, QLD | COMDAIN (UNITYWATER)

$1M ($600K) | AUG 2021 to JAN 2022​

​

Our client Comdain has been delivering network water mains and sewer pump station D&C upgrades to Unitywater since 2007. Allstar was engaged in August 2021 to provide a civil component of the works to upgrade the Noosa Parade Rising Sewer Main. The project was delivered in a busy urban area requiring a detailed approach to stakeholder management to minimise disruption.

OUR SCOPE:

​

  • DN300 existing sewer main relining

  • Construction of new in situ valve pits and footpaths, kerbing and driveways

  • Asbestos pipe removal and disposal

​

​

HIGHLIGHTS/CHALLENGES:

​

  • Confined space entry

  •  Deep excavation with shoring and sheet piling

  • Works delivered adjacent to road and pedestrian walkways within a populated and busy public tourist area

  • Works scheduled around peak holiday periods to avoid water and sewer disruptions

  • Dewatering environmental systems successfully implemented

  • Suspended works and fully demobilised during Bank Holiday and Noosa Triathlon