Our works
NOOSA PARADE RISING SEWER MAIN UPGRADE
SUNSHINE COAST, QLD | COMDAIN (UNITYWATER)
$1M ($600K) | AUG 2021 to JAN 2022​
​
Our client Comdain has been delivering network water mains and sewer pump station D&C upgrades to Unitywater since 2007. Allstar was engaged in August 2021 to provide a civil component of the works to upgrade the Noosa Parade Rising Sewer Main. The project was delivered in a busy urban area requiring a detailed approach to stakeholder management to minimise disruption.
OUR SCOPE:
​
-
DN300 existing sewer main relining
-
Construction of new in situ valve pits and footpaths, kerbing and driveways
-
Asbestos pipe removal and disposal
​
​
HIGHLIGHTS/CHALLENGES:
​
-
Confined space entry
-
Deep excavation with shoring and sheet piling
-
Works delivered adjacent to road and pedestrian walkways within a populated and busy public tourist area
-
Works scheduled around peak holiday periods to avoid water and sewer disruptions
-
Dewatering environmental systems successfully implemented
-
Suspended works and fully demobilised during Bank Holiday and Noosa Triathlon