LOGANHOLME WWTP LIFT PUMP STATION UPGRADE
LOGANHOLME, QLD | DOWNER
(LOGAN CITY COUNCIL)
$7M ($1.2M) | MAY 2021 - DEC 2021
​
Allstar is supporting delivery of the Loganholme WWTP Lift Pump Station Upgrade project being delivered by the Logan Water Infrastructure Alliance – a public and private sector enterprise involving Downer, Logan City Council, Cardno and WSP and one of the largest water infrastructure delivery programs in Australia. The upgrade including new pumps and a penstock will improve operation on the lift station and operator safety.
OUR SCOPE:
​
-
Demolition and removal of existing benching and construction of new benching in the wet well
-
DN700 and DN1000 (2 no.) core holes between 600mm thick wet well/dry well dividing walls
-
Grouting of penstock frame, suction pipe penetrations and pump and duckfoot base plates
-
Demolition and removal of pump plinths for existing pumps
-
Form, reinforce and pour pump and duckfoot plinths for new pumps » Form, reinforce and pour infill landing slabs using cantilevered formwork
HIGHLIGHTS/CHALLENGES:
​
-
Restricted work areas
-
Multiple work fronts with only one gantry crane
-
Concrete placement 20m below ground
-
Weather dependent: development of emergency / contingency plans if wet weather was to develop resulting in releasing valves to flood wet well
-
Removed of over 50T of concrete rubble from existing structure
-
Utilised innovative remote demolition robot to reduce manual handling and fatigue inducing jackhammering
-
Safely delivered the works in parallel with other contractors (SIMOPS)
-
Over 50T of concrete removed over 20m plus below ground level
-
Innovative construction methods used to optimise schedule
-
Challenged design to create less intensive work methodologies
-
Use of demolition robot to minimise personal entering confined space environments