INTERIM BLENDS BULK LOADOUT FACILITY

BRISBANE, QLD | INCITEC PIVOT GIBSON ISLAND (MUNSTER SERVICES GROUP)

$5M ($1.4M) | NOV 2021 - JAN 2022

​

As part of the ongoing structural integrity assessment works at Gibson Island Production Facility, a number of the bulk loadout facilities were required to be taken out of service to facilitate further detailed structural inspections and undertake necessary structural remediation works. Allstar were engaged to provide interim solutions for bulk load out of both blends and straight fertilizer products to maintain continuity in customer supply.

Allstar Adblue Project

OUR SCOPE:

​

  • Service location and non-destructive location of below ground services

  • Construct concrete vehicle access road to new loadout facility

  • Construct new weighbridge structure and below ground drainage

  • Excavate, place and compact subbase for the above structures

  • Formwork, reinforcement, place and finish concrete

  • Site reinstatement, line marking, topsoiling and turfing

​

​

HIGHLIGHTS/CHALLENGES:

​

  • Accelerated delivery schedule due to the urgent nature of the works

  • Design and construct contract resulting in condensed time period between design approval and commencement of construction

  • Successfully staged the works to prevent impact on day-to-day operations

  • Large concrete pours in excess of 70m3 completed

  • Proprietary edge formwork system utilised to mitigate industry skilled labour shortages